Walls and ceiling done; no floor yet!

Today (Nov. 17) marks four weeks of construction and the new master bathroom is taking shape in our Mexican casa. It may not be quite as large as we expected but it will have two sinks with lighted mirrors, a walk-in shower with a rain-style shower head, and a vanity area for Leslie, with a nice boveda ceiling.

The two orange plastic tubes are for electrical wiring. You can see where the two sinks will be on the north wall, with the shower on the left.

The crew is putting in the plumbing and electrical, which means the floor is still dirt. They’re starting on the new laundry room and the new kitchen, too. We think everything is on schedule.

This is where the shower used to be. Once they level the floor, the washer and dryer will sit side-by-side in this space. There will be a floor sink to the right for our maid to use when mopping the tile floors. This will be where the toilet was.

We’re selecting tile, faucets, fixtures and kitchen appliances now. So many choices!

One huge change has already happened. The new master bathroom and kitchen renovation was Phase One. Changes to the front wall and entry into the courtyard was to be part of Phase Two. But our architect, Juan Allera, proposed doing all the work to the front entrance now because it made sense. I asked how much that would add to the total project. The figure was fairly low because it’s mostly labor, so we gave the green light. Most of the front wall is gone now!

Workers start taking down the front wall of the courtyard.

We still hope to be back in our house by Christmas, but some of the appliances are going to take a few weeks to deliver. Fingers crossed!

More to come as work progresses. Hasta luego!

Once the column on the left comes down, the guys will make everything look great. Then we will put planters on top of the half-walls with plants growing up to increase privacy. We removed the gate and plan to replace it. Design to be determined.

Renovation begins!

Leslie and I are finally getting the renovation started on our house — six months later than planned. We hoped to have all the work done in April and May before we moved in. Because of the quarantine, our homeowner’s association did not allow workers into the neighborhood. Later, when that was allowed, we decided it was not a good idea to have people we don’t know coming into our house. We’re taking extra precautions during this pandemic.

Also, as we’ve lived in our new home, our small project grew bigger. The original plan was to get the washer and dryer out of the kitchen to gain more storage and counter space. We planned to get stackable machines and squeeze them into a space in the master bedroom closet, then update the kitchen cabinets with new doors and buy new appliances.

Over the last four-plus months we’ve started thinking bigger, especially after we found a few issues in the master bath. Now we’re adding a new master bathroom onto the front of the house, reworking and improving the closet and other storage, and putting side-by-side laundry units where the bathroom is now. We will also get a new linen closet and utility closet, neither of which exist now. And we’re gutting the 12-year-old kitchen down to the walls. All new cabinetry, all new appliances, more storage and more counter space.

In fact, the kitchen is already gutted and the bathroom will be gone in a few days. Everything was removed carefully by Fernando, who works as a gardener for at least two of our neighbors. Fernando is building a house for his family in Chapala on a shoestring budget, and he can use all the cabinets and appliances from our house.

We feel fortunate to have hired Juan Alera and his daughter Cristina as our architects. Juan has done home building and renovation for years in the Lakeside area. Cristina studied architecture at the university in Guadalajara (where one of her professors was her father) and for a year at a university in France. She speaks English and French in addition to her native Spanish.

Construction begins Oct. 19. Juan says it will take two months, but we’re allowing for three just in case. And since now we have no kitchen and no master bath, and things are about to get very dusty and dirty, we’ve moved out for the rest of this year. Again, we’re very fortunate to have rented a home right here in our neighborhood, just two streets down the hill. It will be easy to go back and get things we need, and to check on construction progress. We hope to be back in our house before Christmas.

Here are a couple of “before” videos:

Here’s the kitchen before the demolition. Lots of changes coming!
And here’s the master bath and closet.